The following data were obtained from a study of the times required to conduct a consumer test

Question:

The following data were obtained from a study of the times required to conduct a consumer test panel study:

The following data were obtained from a study of the

Costs are given in thousands of dollars, time in weeks.
(a) Find the all-normal schedule and cost.
(b) Find the all-crash schedule and cost.
(c) Find the total cost required to expedite all activities from all-normal (case a) to all-crash (case b).
(d) Find the least-cost plan for the all-crash time schedule. Start from the all-crash problem (b). Assume partialcrashing.