Consider the project network below. Suppose the duration of both activities A and D can be reduced

Question:

Consider the project network below. Suppose the duration of both activities A and D can be reduced to 1 day, at a cost of $15 per day of reduction. Also, activities E, G, and H can be reduced in duration by 1 day at a cost of $25 per day of reduction. What is the least-cost approach to crash the project 2 days? What is the shortest “crashed” duration, the new critical path, and the cost of crashing?

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Strategic Managerial Approach

ISBN: 9781119369097

10th Edition

Authors: Jack R. Meredith, Scott M. Shafer, Samuel J. Mantel Jr.

Question Posted: