For one of the risks identified in Exercises 1 through 3 above, construct a cause-and-effect diagram to
Question:
For one of the risks identified in Exercises 1 through 3 above, construct a cause-and-effect diagram to determine possible root causes. Determine which of the possible root causes are probable.
Describe how you would test each probable root cause to determine if it really is a root cause.