For the following questions refer to Figure 13.22. As of week 5, for the project: a. What

Question:

For the following questions refer to Figure 13.22.

As of week 5, for the project:

a. What is the planned value (PV)?

b. What is the earned value of the work completed (EV)?

c. What is actual cost of the project (AC)?

d. What is the value of work remaining?

image text in transcribed

e. What is the CPI?

f. What is estimated cost to complete the project (ETC)?
g. What is the estimated cost at completion (EAC)?
h. What is the estimated cost variance at completion and the percent overrun or underrun?
i. According to EV, is the project ahead of or behind schedule?
j. According to the critical path (A–C–F–H), is the project ahead of or behind schedule?