If an activity on the critical path takes longer than anticipated, then: A. Activities not on the

Question:

If an activity on the critical path takes longer than anticipated, then:
A. Activities not on the critical path have additional slack.
B. Activities not on the critical path have less slack.
C. Additional critical path activities will appear.
D. None of the above.