Industrial Building, Inc., has two project teams installing virtually identical, four-story commercial buildings for a funder in

Question:

Industrial Building, Inc., has two project teams installing virtually identical, four-story commercial buildings for a funder in two separate cities. Both projects have a planned daily cost of 100 and a planned daily EV of 100. The first 6 days for each team have progressed as follows:

 LO4

image text in transcribed

Compare the two projects in terms of general progress and according to CRs.