Industrial Building, Inc., has two project teams installing virtually identical, four-story commercial buildings for a funder in
Question:
Industrial Building, Inc., has two project teams installing virtually identical, four-story commercial buildings for a funder in two separate cities. Both projects have a planned daily cost of 100 and a planned daily EV of 100. The first 6 days for each team have progressed as follows:
LO4
Compare the two projects in terms of general progress and according to CRs.