Iron Butterfly, Inc., submits proposals in response to RFPs and faces three possible outcomes: N1, Iron Butterfly
Question:
Iron Butterfly, Inc., submits proposals in response to RFPs and faces three possible outcomes:
N1, Iron Butterfly gets a full contract; N2, it gets a partial contract (job is shared with other contractors); N3, it gets no contract. The company is currently assessing three RFPs, coded P1, P2, and P3. For P3, the customer will pay a fixed amount for proposal preparation; for P1 and P2, Iron Butterfly must absorb the proposal-preparation costs, which are expected to be high. Based upon project revenues and proposal-preparation costs, the expected profits
($ thousands) are as shown:
To which RFPs would Iron Butterfly respond using the three decision criteria?
Step by Step Answer:
Project Management For Engineering Business And Technology
ISBN: 9780367277345,9781000092561
6th Edition
Authors: John M. Nicholas , Herman Steyn