Of the following, which is not a suggestion to quickly and accurately complete a project on schedule?

Question:

Of the following, which is not a suggestion to quickly and accurately complete a project on schedule?

A. Think clearly, but quickly.

B. Create a visual marker to represent completed work on the workstations.

C. Check for quality as applicable within the final phases.

D. Ask for volunteers to work through the night and into the next day on an implementation.