Suppose, for Problem 13.20, that your PV was 70 and your EV was 95. Recalculate the SPI
Question:
Suppose, for Problem 13.20, that your PV was 70 and your EV was 95. Recalculate the SPI and estimated time to completion for the project with this new data.
Problem 13.20
You are calculating the estimated time to completion for a project of 12 months’ duration and a budgeted cost of $500,000. Assuming the following information, calculate the Schedule Performance Index and the estimated time to completion (figures are in thousands).
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9781292269146
5th Global Edition
Authors: Jeffrey K.Pinto
Question Posted: