The assignment cost of assigning any operator to any machine is given in the following table. Solve
Question:
The assignment cost of assigning any operator to any machine is given in the following table. Solve the minimal assignment problem.
Operators Machine A B C D I 10 5 13 15 II 3 9 18 13 III 10 7 3 2 IV 5 11 9 7 H int: I – B, II – D, III – C, IV – A and optimal assignment cost = 16
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Project Management Theory And Practices
ISBN: 9789332542013
2nd Edition
Authors: Kumar Neeraj Jha
Question Posted: