The Closing Process Group in PMBoK refers to: a. Processes performed to finalize all activities to formally

Question:

The Closing Process Group in PMBoK refers to:

a. Processes performed to finalize all activities to formally close the project or phase

b. Processes performed to complete the work defined in the project management plan

c. Processes required to track, review, and regulate the progress and performance of the project

d. Processes performed to define a new project or new phase of an existing project

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: