The project information for the custom order project of the Air Control Company is presented here. Draw
Question:
The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Calculate the early and late activity times and the slack times. Identify the critical path.
ID | Activity | Predecessor | Time |
---|---|---|---|
A | Order review | None | 2 |
B | Order standard parts | A | 15 |
C | Produce standard parts | A | 10 |
D | Design custom parts | A | 13 |
E | Software development | A | 18 |
F | Manufacture custom hardware | C, D | 15 |
G | Assemble | B, F | 10 |
H | Test | E, G | 5 |