The project information for the custom order project of the Air Control Company is presented here. Draw

Question:

The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Calculate the early and late activity times and the slack times. Identify the critical path.

IDActivityPredecessorTime
AOrder reviewNone2
BOrder standard partsA15
CProduce standard partsA10
DDesign custom partsA13
ESoftware developmentA18
FManufacture custom hardwareC, D15
GAssembleB, F10
HTestE, G5