From the following information, develop an AON project network. Complete the forward and backward pass, calculate activity

Question:

From the following information, develop an AON project network. Complete the forward and backward pass, calculate activity slack and identify the critical path. How many days will the project take?

IDDescriptionPredecessorTime
ASurvey siteNone2
BInstall drainageA5
CInstall power linesA3
DExcavate siteB, C4
EPour foundationD3