Draw a project network from the following information. Which activity is a 'burst' activity? Which activity is
Question:
Draw a project network from the following information. Which activity is a 'burst' activity? Which activity is a 'merge' activity?
ID | Description | Predecessor |
---|---|---|
A | Contract signed | None |
B | Survey designed | A |
C | Target market identified | B |
D | Data collection | B, C |
E | Develop presentation | B |
F | Analyse results | D |
G | Demographics | C |
H | Presentation | E, F, G |