The project manager always involves the team in the creation of the work breakdown structure. What is
Question:
The project manager always involves the team in the creation of the work breakdown structure. What is the most significant benefit derived from this approach?
a. Generation of a more accurate schedule
b. Establishment of the project manager’s authority
c. Generation of a more accurate budget
d. Buy-in from the team doing the work