Which of the following would be considered a cost-estimating relationship (CER)? A. Mathematical equations based on regression
Question:
Which of the following would be considered a cost-estimating relationship (CER)?
A. Mathematical equations based on regression analysis
B. Learning curves
C. Cost–cost or cost–quantity relationships
D. All of the above