You receive a contract to perform testing for an external client. After contract award, the customer provides
Question:
You receive a contract to perform testing for an external client. After contract award, the customer provides you with the test plan to use for the acceptance process. The vice president for Quality Assurance (QA) says that the customer’s test plan is flawed and he will correct the plan that will be used and it will be more in line with the organizational quality program. The contract says that the customer will supply the acceptance test plan. In this case you should A. Use the customer’s test plan B. Use the QA manager’s revised test plan without telling the customer C. Use the QA manager’s revised test plan and inform the customer D. Tell your sponsor that you want to set up a meeting with the customer to resolve the issue
Step by Step Answer:
Project Management Theory And Practice
ISBN: 9780815360711
3rd Edition
Authors: Gary L. Richardson, Brad M. Jackson