13 Caryn Johnson is in charge of relocating (reconductoring) 1,700 ft of 13.8-kilovolt overhead primary line as
Question:
13 Caryn Johnson is in charge of relocating (“reconductoring”) 1,700 ft of 13.8-kilovolt overhead primary line as a result of the widening of the road section in which the line is presently installed. Table 14 summarizes the activities for the project. Draw the network model for her, and carry out the critical path computations.
TABLE 14 Immediate Duration Activity Description predecessors (days)
A Job review – 1 B Advise customers of temporary outage A 0.5 C Requisition stores A 1 D Scout job A 0.5 E Secure poles and materials C,D 3 F Distribute poles E 3.5 G Pole location coordination D 0.5 H Re-stake G 0.5 I Dig holes H 3 J Frame and set poles F, I 4 K Cover old conductors F, I 1 L Pull new conductors J, K 2 M Install remaining material L 2 N Sag conductor L 2 O Trim trees D 2 P De-energize and switch lines B, M, N,O 0.1 Q Energize and phase new line P 0.5 R Clean up Q 1 S Remove old conductor Q 1 T Remove old poles S 2 U Return material to stores R,T 2
Step by Step Answer:
Project Management Processes Methodologies And Economics
ISBN: 9781292039404
1st Edition
Authors: Avraham Shtub