17 For Exercise 16, compute the total slacks and free slacks, and summarize the critical path calculations

Question:

17 For Exercise 16, compute the total slacks and free slacks, and summarize the critical path calculations in a tabular format.

TABLE 15 Immediate Duration Activity Description predecessors (days)
A Conduct feasibility study – 3 B Find potential customer for present boat A 14 C List possible models A 1 D Research all possible models C 3 E Conduct interviews with mechanics C 1 F Collect dealer propaganda C 2 G Compile and organize all pertinent information D, E, F 1 H Choose top three models G 1 I Test-drive all three choices H 3 J Gather warranty and financing information H 2 K Choose one boat I,J 2 L Compare dealers and choose dealer K 2 M Search for desired color and options L 4 N Test-drive chosen model once again L 1 O Purchase new boat B, M, N 3

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: