2 Consider the project plan defined in Table 12. TABLE 12 Activity Scheduled start day Scheduled finish
Question:
2 Consider the project plan defined in Table 12.
TABLE 12 Activity Scheduled start day Scheduled finish day Cost/day A 1 3 $1,000 B 1 5 $5,000 C 3 7 $3,000 D 5 15 $1,000 E 7 22 $2,000 F 7 25 $4,000
a. Write a weekly progress report for each activity based on the above information.
b. Comment on the level of control that can be achieved based on the given information.
TABLE 13 Week 1 Week 2 Week 3 Activity Status Cost Status Cost Status Cost A In process $1,500 Finished $3,000 Finished $3,000 B In process $25,000 Finished $30,000 Finished $30,000 C In process $7,000 Finished $10,000 Finished $10,000 D Not started 0 In process $5,000 In process $7,000 E Not started 0 Not started 0 In process $10,000 F Not started 0 In process $10,000 In process $20,000