3 A cost schedule control system produces weekly reports.The reports for weeks 1, 2, and 3

(assume 5 working days each week) are shown Table 13.

3 In Exercise 2, an estimate of the “percent complete” for each activity each week is reported in Table 14.Redo parts

(a) and (b).
TABLE 14 Percent complete Activity Week 1 Week 2 Week 3 A 50 100 100 B 30 100 100 C 10 100 100 D 0 20 60 E 0 0 25 F 0 30 40