3 A cost schedule control system produces weekly reports.The reports for weeks 1, 2, and 3 (assume...
Question:
3 A cost schedule control system produces weekly reports.The reports for weeks 1, 2, and 3
(assume 5 working days each week) are shown Table 13.
3 In Exercise 2, an estimate of the “percent complete” for each activity each week is reported in Table 14.Redo parts
(a) and (b).
TABLE 14 Percent complete Activity Week 1 Week 2 Week 3 A 50 100 100 B 30 100 100 C 10 100 100 D 0 20 60 E 0 0 25 F 0 30 40
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Processes Methodologies And Economics
ISBN: 9781292039404
1st Edition
Authors: Avraham Shtub
Question Posted: