9 Planmatics is undertaking a modernization program. The set of activities in Table 16 has been defined

Question:

9 Planmatics is undertaking a modernization program. The set of activities in Table 16 has been defined for refurbishing one of its wave soldering machines.The AOA network is given in Fig. 5.

a. Find the critical path, total slacks, and free slacks.

b. Find the probability of completion within 45 days.

TABLE 16 Crash date Maximum possible Expediting cost Activity (days) (days) compression (days) per day ($)
A 6 2 0 —
B 2 0 1 50 C 12 3 2 80 D 8 1 2 175 E 7 2 1 100 F 16 4 0 —
G 23 2 1 100 H 25 5 3 300 I 4 1 1 1,000

image text in transcribed

c. Find the minimum cost increase to reduce the expected project duration by 1 day.

d. Find the minimum cost increase to reduce the expected project duration by 2 days.

e. Find the minimum project duration and the expected cost increase.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: