Consider the precedence relations given in Table 21. a. Draw an early-start Gantt chart. b. Draw the

Question:

Consider the precedence relations given in Table 21. 

TABLE 21 Activity ABCDEFGH I Immediate predecessors - A A A B C, D E, F D G, H Weeks 1 4 3 7 6 6270 9 4

a. Draw an early-start Gantt chart. 

b. Draw the AON network for this project. 

c. Draw the AOA network. 

d. Generate all possible paths for the AOA network, calculate their duration, and analyze the findings. 

e. Calculate ES, EF, LF, and LS for each activity. 

f. Calculate the slacks for the activities.