Space Module Assembly. An aerospace company has received a contract from NASA for the final assembly of
Question:
Space Module Assembly. An aerospace company has received a contract from NASA for the final assembly of a space module for an upcoming mission. A team of engineers has determined the activities, precedence constraints, and time estimates as given in Table 19.
a. Draw the AOA network for this project.
b. Calculate total slacks and free slacks, and interpret their meaning.
c. Determine the critical path and interpret its meaning.
d. Construct a Gantt chart and identify scheduling flexibilities.
Step by Step Answer: