Consider the project plan defined in Table 12. A cost schedule control system produces weekly reports. The

Question:

Consider the project plan defined in Table 12. 

TABLE 12 Activity A B C  E F Scheduled start day 113577 Scheduled finish day 3 5 7 15 22 25 Cost/day $1,000

A cost schedule control system produces weekly reports. The reports for weeks 1, 2, and 3 (assume 5 working days each week) are shown Table 13. 

a. Write a weekly progress report for each activity based on the above information. 

b. Comment on the level of control that can be achieved based on the given information.

TABLE 13 Activity A B C D E F Week 1 Status In process In process In process Not started Not started Not