Develop the AOA network for the project in Exercise 6. Calculate the early time and the late

Question:

Develop the AOA network for the project in Exercise 6. Calculate the early time and the late time of each event and the early start, early finish, late start, and late finish of each activity.


Data in Exercise 6.

Develop a list of activities for the project “designing a new house.” Estimate the duration of each activity, and define the precedence relations among them. How much uncertainty exists in each activity? The project ends when the plans and documents have been finalized.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management Processes Methodologies And Economics

ISBN: 9780130413314

2nd Edition

Authors: Avraham Shtub, Jonathan F. Bard, Shlomo Globerson

Question Posted: