A key stakeholder requests additional features late in the project. What should the project manager do? a)

Question:

A key stakeholder requests additional features late in the project.

What should the project manager do?

a) Approve the request to satisfy the stakeholder

b) Reject the request to avoid scope creep

c) Evaluate the impact of the request and proceed through the change control process

d) Implement the features and adjust the project plan later