A project manager is preparing the final project report. What should be included to address stakeholder management?
Question:
A project manager is preparing the final project report. What should be included to address stakeholder management?
a) Detailed project schedule
b) Summary of stakeholder engagement activities and any issues encountered
c) List of project stakeholders
d) Project risk assessment
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: