A stakeholder identifies a potential quality issue in a critical deliverable. What should the project manager do?
Question:
A stakeholder identifies a potential quality issue in a critical deliverable. What should the project manager do?
a) Ignore the quality issue and continue with the project
b) Evaluate the impact of the quality issue and take corrective actions if necessary
c) Update the project schedule
d) Request additional resources
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: