All of the following are true regarding the project plan except: A. Some of its inputs are
Question:
All of the following are true regarding the project plan except:
A. Some of its inputs are outputs from other Planning processes.
B. It’s used to guide the project Executing and Controlling processes and is the baseline used to measure project performance.
C. It consists of one document that should be formally approved and signed by stakeholders.
D. It contains things like the WBS, project schedule, and resource assignments.