During a project review, a stakeholder requests additional resources for a specific activity. What should the project

Question:

During a project review, a stakeholder requests additional resources for a specific activity. What should the project manager do?

a) Implement the additional resources immediately

b) Evaluate the impact of the additional resources and process the request through the change control system

c) Reject the additional resources to avoid changes

d) Update the project schedule