Question: What is the best approach for handling procurement changes during a project? a) Ignore all procurement changes to avoid delays b) Evaluate the impact of
What is the best approach for handling procurement changes during a project?
a) Ignore all procurement changes to avoid delays
b) Evaluate the impact of the changes and process them through the change control system
c) Implement the changes immediately to keep stakeholders happy
d) Focus only on high-impact changes