You are managing a project to install a new postage software system that will automatically print labels

Question:

You are managing a project to install a new postage software system that will automatically print labels and administer postage for certified mailings, overnight packages, and other special mailing needs.

You’ve attempted to gain the cooperation of the business analyst working on this project and need some answers. She is elusive and tells you that this project is not her top priority. To avoid situations like this in the future, you should:

A. Establish the business analyst’s duties well ahead of due dates and tell her you’ll be reporting on her performance to her functional manager.

B. Establish the business analyst’s duties well ahead of due dates and tell her you are expecting her to meet these expectations because the customer is counting on the project meeting due dates to save significant costs on their annual mailings.

C. Negotiate with the business analyst’s functional manager during the planning process to establish expectations and request to participate in the business analyst’s annual performance review.

D. Negotiate with the business analyst’s functional manager during the planning process to establish expectations and inform the functional manager of the requirements of the project. Agreement from the functional manager will assure the cooperation of the business analyst.