A _________ is a deliverable at the lowest level of the WBS, where it can be appropriately
Question:
A _________ is a deliverable at the lowest level of the WBS, where it can be appropriately assigned to and managed by a single accountable person. A. WBS dictionary B. budget item C. control account D. work package