As the project manager for a software development project, you are helping to develop the project schedule.

Question:

As the project manager for a software development project, you are helping to develop the project schedule. You decide that writing code for a system should not start until users sign off on the analysis work. What type of dependency is this?

a. technical

b. mandatory

c. discretionary

d. external LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: