Assume the following information for an IT project. Probability of Failure Consequences of Failure Maturity = .7

Question:

Assume the following information for an IT project.
Probability of Failure Consequences of Failure
Maturity = .7 ……………………………. Cost = .9
Complexity = .7 …………………………. Schedule = .7
Dependency = .5 ………………………… Performance = .3
Client Concerns = .5 …………………….. Future Business = .5
Programmer Skill = .3
Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?