Calculate the fully loaded cost of labor for your Project Engineer using the following data: Hourly rate:
Question:
Hourly rate: …………………………….. $40/hr
Estimated hours of work: ………………. 120
Overhead rate: …………………………. 65%
Personal time: ………………………….. 15%