Consider the following information that you have compiled regarding the steps needed to complete a project. You

Question:

Consider the following information that you have compiled regarding the steps needed to complete a project. You have identified all relevant steps and have made some determinations regarding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities.
Activity Predecessors
A – Survey site ……………………………………….. -
B – Install sewer and storm drainage ………………… A
C – Install gas and electric power lines ………………. A
D – Excavate site for spec house …………………….. B, C
E – Pour foundation …………………………………. D
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: