Consider the partial resource-loading chart shown below. Suppose that you can commit a maximum of eight resource

Question:

Consider the partial resource-loading chart shown below. Suppose that you can commit a maximum of eight resource hours per day.
a. What are the dates on which project resources are overallocated?
b. How should the resource-loading table be reconfigured to correct for this overallocation?
c. Now suppose that the maximum number of resources hours per day you can commit is reduced to six. How would you reconfigure the resource-loading table to adjust for this number? What would be the new project completion date?