Given the information in the following table, draw the AOA network. Using the same information, enter the
Question:
Given the information in the following table, draw the AOA network. Using the same information, enter the data into MSP assuming a seven-day workweek.
(To change the calendar in MSP from its five-day week default click “Help, type “calendar change,” and follow directions.) Develop the appropriate AON network and Gantt chart. Using any method you wish, LO6 find the critical path and critical time for the network.
Then find the slack for all activities.
Activity Predecessor Duration a — 5 days b —7 c —4 d a6 e b9 f b6 g c4 h
d, e 6 i
d, e 8 j
f, g, h 9 k i 10 l j9
Step by Step Answer:
Related Book For
Project Management In Practice
ISBN: 9780470121641
3rd Edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Scott M. Shafer, Margaret M. Sutton
Question Posted: