Harry is the project manager for his organization. Elizabeth, his manager, has asked that Harry create a

Question:

Harry is the project manager for his organization. Elizabeth, his manager, has asked that Harry create a bottom-up cost estimate for a new project. What is a bottom-up cost estimate?

A. Last year’s budget plus 20 percent to equal the current year’s budget B. This year’s budget with a 20 percent plus or minus shift in the bottom line C. The process of working toward a zero balance as the bottom line in a budget D. The process of creating a detailed estimate for each work package in a WBS