You are the project manager of the JHN Project. You have estimated the project will cost $129
Question:
You are the project manager of the JHN Project. You have estimated the project will cost $129 for each unit installed. There are 1,200 units on this project. What type of estimate is this?
A. Bottom-up estimate B. Top-down estimate C. Analogous estimating D. Parametric estimating