You are the project manager for your organization. Management has asked that you create a detailed cost
Question:
You are the project manager for your organization. Management has asked that you create a detailed cost estimate for a new solution they’d like you to implement. What type of project estimating must account for every expense within a project before the work begins?
A. Bottom-up estimating B. Top-down estimating C. Zero-based budgeting D. Parametric estimating