How must the Gantt chart you drew in problem 22 be changed if you were told that
Question:
How must the Gantt chart you drew in problem 22 be changed if you were told that C and D could not begin until B was completed, and that G could not begin until C was completed? What happens to the project completion time?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer: