If the actual cost for a WBS item is $1,500 and its earned value is $2,000, what
Question:
If the actual cost for a WBS item is $1,500 and its earned value is $2,000, what is its cost variance, and is it under or over budget?
a. The cost variance is $500, which is over budget.
b. The cost variance is $500, which is under budget.
c. The cost variance is $500, which is over budget.
d. The cost variance is $500, which is under budget.