In the LOGON project suppose the status of the project as of Week 22 is as follows:
Question:
In the LOGON project suppose the status of the project as of Week 22 is as follows:
BCWS = $628,000 ACWP = $640,000 BCWP = $590,000 Answer the following questions:
a. What is the earned value of the project as of Week 22?
b. Compute AV, SV, and CV.
c. Using a graph similar to Figure 11-8, plot BCWS, ACWP, and BCWP. Show AV, SV, and CV. Determine TV from the graph.
d. Compute SPI and CPI. Has the project performance improved or worsened since Week 20?
e. Using BCAC = $990,000, compute ETC and EAC. How does EAC compare to the Week 20 estimate of $1,222,593? Draw a status chart similar to Figure 11-12 and use it to determine the revised completion date. How does it compare to the revised date (Week 48–49) as of Week 20?
f. Are the results from Part
(e) consistent with the results from Part
(d) regarding improvement or deterioration of project performance since Week 20?
Step by Step Answer:
Project Management For Business Engineering Principles And Practice
ISBN: 286248
2nd Edition
Authors: John M. Nicholas