___________ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule
Question:
___________ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
A. Crashing B. Fast tracking C. De-scoping D. Parametric modeling
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
An Introduction To Project Management With A Brief Guide To Microsoft Project 2016
ISBN: 9781544701899
6th Edition
Authors: Kathy Schwalbe
Question Posted: