John is the project manager for his organization, and hes creating the project management plan. He is
Question:
John is the project manager for his organization, and he’s creating the project management plan.
He is reviewing the project scope baseline with his project team so that they’ll understand the requirements and direction of the project. Which of the following is the correct definition of the project scope baseline?
A. It is all the work, and only the required work, to meet the project objectives.
B. It is the combination of the project scope statement, the WBS, and the WBS dictionary.
C. It is the combination of the project requirements, the project scope, and the WBS.
D. It the consideration of the project requirements, assumptions, and constraints that affect the project planning.