You are the project manager for your organization and are creating the project schedule. You know that

Question:

You are the project manager for your organization and are creating the project schedule. You know that a project schedule is composed of all the following components except for which one?

A. The network of all of the tasks within the project B. The assignment of resources C. The budget for the project D. The reflection of the WBS