Pierre is the project manager of a project to upgrade all of the print servers and printers
Question:
Pierre is the project manager of a project to upgrade all of the print servers and printers within his company. The deliverables require that each floor have a pool of print devices, with the exception of the graphics department. They will have several different types of printers, including two high-end color printers. Marty, the sales manager, requests that his department receive a color printer as well. What is the first process Marty should follow?
A. Submit funding for the color printer.
B. Submit a Project Change Request form.
C. Submit a change impact statement.
D. Submit a proposal on how the new printer will help his department be more productive.